The EVO Group
Project Scope:
Demolition of a four-story office block in Sheffield, built in 2001 and due to subsidence required to be demolished.
Project Constraints & Challenges:
Delivery of the works within a densely populated commercial area.
Traffic and people management.
24/7 noise, dust and vibration monitoring.
Segregation and processing of materials on an extremely confined site.
Achievements:
No environmental impact complaints for noise or dust.
Uninterrupted use of roads surrounding the site.
The project was delivered on time and on budget.
Project Details
DURATION
10 Weeks
CLIENT
The EVO Group
LOCATION
Sheffield